  • We've not done an extension, but we have done some heafty work on a couple of places now.
    Our rule of thumb, stolen from architect friends, is that anyone who can't float themselves for materials and labour for the first 4 weeks doesn't get the work.

    So yes...
    Plan out your milestones.
    Something like...
    Ground work complete - 20%
    Structure topped out - 20%
    First fix - 20%
    Second fix and fitout - 20%
    Snag list cleared, certification and paperwork in place, job signed off - 20%

    You need to agree clear definitions of these stages with your main contractor before you start.