  • Heh, our ISP is blaming the looting for an outage

    Start Date/ Time: 13:25
    Duration: 3hrs 25minutes
    Service Affected: IP Connectivity
    Priority: 1
    Location: Interxion Data Centre London/Level3 Data Centre Braham Street

    Incident Details We are currently experiencing an issue affecting a link between these two data centres used to transport internet traffic.

    Update Summary: Due to unprecedented internet usage as a result of the recent events in London and surrounding areas, there are currently capacity issues affecting some of Adapt’s network links. Engineers are working to mitigate the impact of this, but in the meantime, please limit the use of high bandwidth applications (e.g. streaming video) wherever possible.