Anyone had their incoming electricity supply moved? The bit that the network operator has to do, not just the meter.
Keen to hear stories/ tips. My incoming supply is in a cupboard in the bedroom at very low level, and looka sub optimal for a lot of other reasons. I'm having a new consumer unit and a partial rewire anyway, so it feels like it's a thing worth doing and worth doing now (albeit it'll need the network operator, the supplier and the electrician to all do their own bits)
For DNO moves I'd not expect it to be a quick process, hope for 3 months, assume 6 months and don't expect it to be done and you're unlikely to be disappointed.
This is my experience from a commercial perspective where we were doing a fair amount of connections, disconnections and moves.
Anyone had their incoming electricity supply moved? The bit that the network operator has to do, not just the meter.
Keen to hear stories/ tips. My incoming supply is in a cupboard in the bedroom at very low level, and looka sub optimal for a lot of other reasons. I'm having a new consumer unit and a partial rewire anyway, so it feels like it's a thing worth doing and worth doing now (albeit it'll need the network operator, the supplier and the electrician to all do their own bits)