• Some paint starting to go on here. It's a F&B colour called Dimity but mixed by Dulux.
    4 weeks into a 3 week build😭
    Some cabinets starting to get built today. Small ammount of surgery required to the top of the tall cupboard doors as it seems the lowering of the ceiling means that they are out by 15mm.
    Lights and some sockets fitted. Grouting done. Hopefully, most of it will be done by Tuesday.