• Allowing 7 days for 3 people, 2 to dig, 2 to prep and concrete, 2 to lay, 1 to finish. Materials: 8 tons concrete, 1 ton mortar (2 if stone surface), £50 for pipe and shingle, £50 mixer hire (if not local), 1skip @250. Should be about £4700.
    Note: that's contingent on what's found in the ground when digging.

    Get them to fix into that downpipe with a 3 or 4 degree fall to the edge of the patio, allowing for a 2 degree fall to the far side of the lawn.