• That’s ours done for this year - start back again on the 3rd. Maxlight rear window (not as big as Chris’) arrives on the 16th so should have glazing done by end of that week, same as electrics.
    Should get a decent amount of storage under those stairs and downstairs shower room and utility are small but adequate.

  • Cheers dude! Heading down on Tuesday to check it out and finalise electrical plans. Then again the following Wednesday as that should be when most of the glazing installed. Will post some more pics