I had similar done on my extension plus one new radiator in the existing so a total of 6. The plumbers did the first fix and it took a day which included one going to the plumbers merchant which too 1-2 hours and then 2 hours sitting in the van to drag it out to a day.....
I did the second fix which took half a day.I would say 2-3 days at the most
Thanks, priced everything up as best i could for rads/pipes/valves etc. just don’t have a frame of reference for how long to install.