Thanks all! @hvsds - I've been considering that sort of insulation - how long did that process take you? Would probably skip the draughtex if I insulate - thought it might be a quick fix alternative.
-
really not long at all, all things considered - with a staple gun and a stanley knife in hand, did about 50sqm in less than a day.
that was with all the boards lifted already, actually - which was probably another day or so to lift them all, remove the old nails, and then another day afterwards to re-nail them all down again.
not used it, but heard good things - both from youtube DIYers and the chap who sanded our floors.
worth thinking about insulating the ground floor if it's suspended and there's room?
I used this method:
https://www.youtube.com/watch?v=UCGpRpKKGV8
mainly as it was cheaper than this method:
https://www.youtube.com/watch?v=rXJDwjkoEkQ