  • I'm going to dig out the kitchen floor because I suspect it's made of crap, and I'd like to insulate it and also make it so that the finished floor level is the same as the floorboards in the room next to it.

    Will dig down 300mm ish, do hardcore/sub-base > sand > dpm > insulation > dpm again > concrete > screed

    Actual question is about the last one - what's the difference between CEMENT-BASED LEVELLING COMPOUND and CEMENT-BASED LEVELLING SCREED ?

  • its for different depths of cover, first one is 0-10mm and the second one is for 3-50mm (says on the bag)

  • thank you! one of those things that probably should have been self-explanatory really - lots of first time bits and bobs for me at the moment.