Non-payment of suppliers' charges
2(1) Where a customer has not, within the requisite period, [made all the relevant payments], the supplier
may--
(a) install a pre-payment meter on the premises; or
(b) disconnect the premises,
(2) The power of a supplier under sub-paragraph (1)(a) or (b) may not be exercised-- (a) as respects any amount which is genuinely in dispute
.
If your sure you don't owe them (or the previous supplier that they took over) and your disputing it, they shouldn't be trying to install a payment meter.
@nick_h.
If they actually had a warrant, it looks like they will need a new one as they had 28 days.
Page 245/246
https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/490992/Electricity_Act_1989__Energy_Bill_2015-16_Keeling_Schedule_.pdf
If your sure you don't owe them (or the previous supplier that they took over) and your disputing it, they shouldn't be trying to install a payment meter.
1 Attachment