Usually distribution board installation includes proper testing of all the circuits and provision of paperwork. The first EICR is often the most expensive as it's considered good practice to remove and check all sockets and switches. After that it's normal to carry out a smaller inspection to check deterioration.
For the EICR? replacing the consumer unit, which has seen better days. But if I’m going to do that, best to get wiring checked out, 8 circuits total.
So I’m thinking circa £300 for the ECIR hopefully nothing major comes up.
Consumer Board, labour, testing circa £100