I'm going down the pilings route using cardboard forms.
At some point, I should possibly have an engineer do some fag packet calculations, but my own suggest that 12 pilings, each 300mm diameter & 600m deep, using high strength concrete and a bit of rebar, should support many times the weight of the office I have planned.
It will also use 6 - 8 times less concrete than a slab, meaning I can mix it myself (once I figure out a way to get the cement mixer down the side of the house...).
Ah yes I forgot you were going down the form route. I guess the main thing would be your soil condition. If you can get them down to clay they should be rock solid. I'm guessing 12 piles will be 2m spacing?
I'm going down the pilings route using cardboard forms.
At some point, I should possibly have an engineer do some fag packet calculations, but my own suggest that 12 pilings, each 300mm diameter & 600m deep, using high strength concrete and a bit of rebar, should support many times the weight of the office I have planned.
It will also use 6 - 8 times less concrete than a slab, meaning I can mix it myself (once I figure out a way to get the cement mixer down the side of the house...).