  • ???? Should have been done and certified when the slab was poured. Test cubes should have been poured, soaked and pressure tested.

    There are specialist grout products you can get (or alternatively go old school and use sand, cement and water) to fill the holes left behind once whirly bolts have been removed and formwork has been struck, it has the potential to be messy overhead but mixing it stiff, forcing it it and covering it whilst setting should get the job done.

  • Dunno. It's a job I've been tasked with. I asked if it was strength testing but it's not. Something to do with composition of said concrete.

    To be honest it'll be above ceiling tiles and probably not on show. However work and the client are being pretty vague about it and I'm trying to cover bases here.

    I can tell you now that formwork won't happen. It'll be quick and dirty. Work just said 'Buy Pollyfilla' but I know that won't work. Meh...