Right so I've got freshly plastered walls and no radiators and I'm getting pretty cold.
What's the order of works now?
Mist coat
1st coat where radiators will be
1st coat everywhere else - or end of the day
2nd coat behind radiators
fit radiators
2nd coat everywhere else
lay floor
3rd coat
Skirting