  • the problem with concreting over the pebbles is that there will be a moisture trap, and dependent on new layer depth, this will blow due to freeze/thaw quicker or slower.

    so either remove pebbles and scabble out so there's a good 150mm new slab depth to pour, or consider leaving as is and put a deck on top

  • Freeze/thaw not an issue (Singapore) but the moisture pocket thing I had not considered! Good point and thank you! Agree with you and @dammit ref deck is just that I want to build an outside kitchen/bbq area.
    Thinking combo of deck and mini foundation area.