Be aware that you'll have all the boards up at this point, so if you want any central heating work done, then I'd consider doing it before putting them back down. Also, generally speaking, it will damage the boards to some extent, so you may need to re-finish if you have varnished boards.
It's also the time to decide if you want to add any extra outlets, eg. near your TV, or in any room where you are lacking.
As it's a lot of money, get an actual quote of what the "re-wire" will entail. For example, will they re-plaster where they have had to remove any?
Just had an electric check. I suspected it would be bad, some of the work seemed to have been done by an enthusiastic amateur, but I wasn't expecting:
**thank you for your enquiry and as requested have visited the above premises and carried out a full test and inspection of the electrical installation and list deviations from IEE Wiring regulations as follows.
– 5 x twin and 2 s single sockets. (2)
frame and extension leads plugged into extension leads. (2)
bath. (2)
(1)
Recommendations
Taking the above into consideration I would strongly recommend a complete rewire.**
£3900 plus VAT.